top of page

CONSTRUCTION UPDATES
Look-Ahead Schedule: August 10 - August 24
August 10 - August 24 NiCor Utility relocations Weeks of August 10th to August 24th Utility Work – Advance work for the Polaris Stormwater Improvement Project NiCor has completed relocation work of six- and eight-inch gas service mains, and in some cases replaced two-inch private gas services to homes on Kilpatrick and 105th. This work is required as these utilities conflict with the proposed sewer improvements and replacing the gas services is needed as some of these service


Look-Ahead Schedule: July 13 - July 27
July 17 - July 27 NiCor Utility relocations Weeks of June 29th to July 13th Utility Work – Advance work for the Polaris Stormwater Improvement Project NiCor has completed relocation work of six- and eight-inch gas service mains, and in some cases replaced two-inch private gas services to homes on Kilpatrick and 105th. This work is required as these utilities conflict with the proposed sewer improvements and replacing the gas services is needed as some of these service lines a


Look-Ahead Schedule: June 29 - July 13
June 29 - July 13 NiCor Utility relocations Weeks of June 29th to July 13th Utility Work – Advance work for the Polaris Stormwater Improvement Project NiCor has completed relocation work of six- and eight-inch gas service mains, and in some cases replaced two-inch private gas services to homes on Kilpatrick and 105th. This work is required as these utilities conflict with the proposed sewer improvements and replacing the gas services is needed as some of these service lines a


bottom of page
