top of page

CONSTRUCTION UPDATES
Look-Ahead Schedule: October 16 - October 31
October 16 - October 31 NiCor Utility relocations Weeks of October 2 to October 16th Utility Work – Advance work for the Polaris Stormwater Improvement Project NiCor has begun landscaping operations and should be completed by October 28th. Any additional watering by residents is encouraged and will help the newly placed sod establish itself. Polaris Sewer Improvement Project Weeks of October 16 to October 31st Pavement markings will be placed next week. Center line yellow shi


Look-Ahead Schedule: October 2 - October 16
October 2 - October 16 NiCor Utility relocations Weeks of October 2 to October 16th Utility Work – Advance work for the Polaris Stormwater Improvement Project NiCor has completed relocation work of six- and eight-inch gas service mains, and in some cases replaced two-inch private gas services to homes on Kilpatrick and 105th. NiCor has been slow to restore sidewalks, and grassy area's impacted by their work. The Village and CBBEL is working on expediting those efforts. Polari


Look-Ahead Schedule: September 4 - September 18
September 4 - September 18 NiCor Utility relocations Weeks of September 4th to September 18th Utility Work – Advance work for the Polaris Stormwater Improvement Project NiCor has completed relocation work of six- and eight-inch gas service mains, and in some cases replaced two-inch private gas services to homes on Kilpatrick and 105th. NiCor will be resuming a sidewalk restoration and landscaping the third week of September. What you can expect: This work will primarily be in


bottom of page
