top of page

CONSTRUCTION UPDATES
Look-Ahead Schedule: June 29 - July 13
June 29 - July 13 NiCor Utility relocations Weeks of June 29th to July 13th Utility Work – Advance work for the Polaris Stormwater Improvement Project NiCor has completed relocation work of six- and eight-inch gas service mains, and in some cases replaced two-inch private gas services to homes on Kilpatrick and 105th. This work is required as these utilities conflict with the proposed sewer improvements and replacing the gas services is needed as some of these service lines a


Look-Ahead Schedule: June 15 - June 29
June 15 - June 29 NiCor Utility relocations Weeks of June 15th to June 29th Utility Work – Advance work for the Polaris Stormwater Improvement Project NiCor has completed relocation work of six- and eight-inch gas service mains, and in some cases replaced two-inch private gas services to homes on Kilpatrick and 105th. This work is required as these utilities conflict with the proposed sewer improvements and replacing the gas services is needed as some of these service lines a


Look-Ahead Schedule: June 1 - June 15
June 1 - June 15 NiCor Utility relocations Weeks of June 1st to June 15th Utility Work – Advance work for the Polaris Stormwater Improvement Project NiCor has completed relocation work of six- and eight-inch gas service mains, and in some cases replaced two-inch private gas services to homes on Kilpatrick. Nicor will continue working on 105th from Kolmar to Kildare. This work is required as these utilities conflict with the proposed sewer improvements and replacing the gas se


bottom of page
