top of page

CONSTRUCTION UPDATES
Look-Ahead Schedule
Look-Ahead Schedule Starting Nov. 3, 2025 NiCor Utility relocations Weeks of March 23, 2026 to April 6, 2026 Utility Work- Advance work for the Polaris Stormwater Improvement Project Currently NiCor is performing relocation work which includes gas service mains 6 and 8 inches and, in some cases, replacing private gas services two inches to homes on Kilpatrick. Additional crews will also be working at school entrance on Kenton Ave. and will soon be working from Kilpatrick to K
August 27, 2024
The Village is pursuing funding for the project through the Federal Emergency Management Agency (FEMA) Hazard Mitigation Grant Program...
Construction Scheduled for Fall 2025
Construction is scheduled to begin in Fall 2025. Please check back for updates.
bottom of page
